The Municipality is excited with the progress made in rebuilding the oThongathi Water Treatment Plant which was damaged by the recent floods. All is on track. The earthwork is 80 per cent completed while civil structures are at 90 per cent completed. Mechanical, electrical, as well as electronic works are 70 per cent complete.
Contractors continue working hard to ensure that water is fully restored by the projected timeline, which is the end of October.